Utility outages

In order to perform necessary maintenance, inspection or equipment modifications, interruptions in building services or systems will take place. In all cases, every attempt will be made to keep the inconvenience to a minimum. If you have any questions, please contact one of Facilities Management’s service desks:

Academic division
(434) 924-1777

Health system division
(434) 924-2267

Outage Subscription Manager

Planned & Emergency Utility Outages


  1. 5/10/2021 8:00:00 AM thru 5/28/2021 12:00:00 AM
    Affected Buildings: COLLINS WING
    Affected Utilities: Room Closure
    Reason: LTHW Phase 1A - Project
  2. 5/11/2021 5:30:00 AM thru 5/11/2021 6:30:00 AM
    Affected Buildings: SHERIDAN G. SNYDER TRANSLATIONAL RESEARCH BUILDING
    Affected Utilities: HVAC
    Reason: Snyder Small Animal MRI - Project
  3. 5/11/2021 7:00:00 AM thru 5/11/2021 8:00:00 AM
    Affected Buildings: SCOTT STADIUM
    Affected Utilities: Electricity Normal Power
    Reason: Deactivating Jumbotron Switchgear panel to install camlock tails for graduation power feed
  4. 5/11/2021 7:00:00 AM thru 5/11/2021 10:00:00 AM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: Fire Alarm System
    Reason: ED Operating Rooms & Bed Tower Addition - Project
  5. 5/12/2021 12:01:00 AM thru 5/13/2021 6:00:00 AM
    Affected Buildings: JAG GROUNDS (PER LEASE EXTENTS), STUDENT FACULTY CENTER (LAW)
    Affected Utilities: Chilled Water, Chilled Water
    Reason: North Grounds Mech Plant & Distribution - To pull wire and land feeders for the new Chiller 3 as part of the plant upgrade.
  6. 5/12/2021 5:00:00 AM thru 5/12/2021 7:00:00 AM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: Fire Alarm System
    Reason: ED Operating Rooms & Bed Tower Addition - Project
  7. 5/13/2021 5:00:00 AM thru 5/13/2021 7:00:00 AM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: Fire Alarm System
    Reason: ED Operating Rooms & Bed Tower Addition - Project
  8. 5/13/2021 7:00:00 AM thru 5/13/2021 11:00:00 AM
    Affected Buildings: MCLEOD HALL
    Affected Utilities: Domestic Water
    Reason: P05811 - McLeod School of Nursing Second Floor Simulation Center - Silson, Kevin - Project
  9. 5/14/2021 7:00:00 AM thru 5/14/2021 9:00:00 AM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: Fire Alarm System
    Reason: ED Operating Rooms & Bed Tower Addition - Project
  10. 5/14/2021 9:00:00 AM thru 5/14/2021 10:00:00 AM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: Fire Alarm System
    Reason: ED Operating Rooms & Bed Tower Addition - Project
  11. 5/14/2021 7:00:00 PM thru 5/15/2021 3:00:00 AM
    Affected Buildings:
    Affected Utilities: Electricity (Emergency Power), Electricity (Emergency Power)
    Reason: Maintenance
  12. 5/15/2021 7:00:00 AM thru 5/15/2021 8:00:00 AM
    Affected Buildings: PINN HALL
    Affected Utilities: Electricity
    Reason: Maintenance
  13. 5/15/2021 8:00:00 AM thru 5/15/2021 9:00:00 AM
    Affected Buildings: PINN HALL
    Affected Utilities: Electricity
    Reason: Maintenance
  14. 5/15/2021 8:00:00 AM thru 5/15/2021 12:00:00 PM
    Affected Buildings: STACEY HALL
    Affected Utilities: Electricity
    Reason: Maintenance
  15. 5/16/2021 7:00:00 AM thru 5/16/2021 5:00:00 PM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: Electricity
    Reason: Maintenance
  16. 5/25/2021 7:00:00 AM thru 5/25/2021 8:00:00 AM
    Affected Buildings: SCOTT STADIUM
    Affected Utilities: Electricity Normal Power
    Reason: Deactivating Jumbotron Switchgear panel to remove camlock tails for graduation power feed
  17. 5/25/2021 7:00:00 AM thru 5/25/2021 3:00:00 PM
    Affected Buildings: SHERIDAN G. SNYDER TRANSLATIONAL RESEARCH BUILDING
    Affected Utilities: Vacuum Systems
    Reason: Maintenance
  18. 6/26/2021 5:00:00 AM thru 6/27/2021 12:00:00 AM
    Affected Buildings: BALZ-DOBIE HOUSE, BOND HOUSE, BONNYCASTLE HOUSE, CAUTHEN HOUSE, COURTENAY HOUSE, DABNEY HOUSE, DILLARD (SUITES X31-X40), DILLARD (SUITES X41-X48), DILLARD (SUITES X49-X50), DILLARD (SUITES X51-X58), DILLARD (SUITES X59-X60), DUNGLISON HOUSE, ECHOLS HOUSE, EMMET HOUSE, ERN COMMONS, FITZHUGH HOUSE, GIBBONS HOUSE, GILDERSLEEVE HOUSE, GOOCH (SUITES X01-X06), GOOCH (SUITES X07-X10), GOOCH (SUITES X11-X20), GOOCH (SUITES X21-X30), HANCOCK HOUSE, HARRISON HOUSE, HOXTON APTS, HUMPHREYS HOUSE, JOHNSON HOUSE, KELLOGG HOUSE, KENT HOUSE, LEFEVRE HOUSE, LILE-MAUPIN HOUSE, LONG HOUSE, MALLET HOUSE, MALONE HOUSE, MARY MUNFORD HOUSE, MCGUFFEY HOUSE, METCALF HOUSE, NORRIS HOUSE, PAGE HOUSE, ROBERTA GWATHMEY HOUSE, ROGERS HOUSE, SHANNON HOUSE, SHEA HOUSE, SMITH HOUSE, TUCKER HOUSE, TUTTLE-DUNNINGTON HOUSE, VAUGHAN HOUSE, VENABLE HOUSE, WATSON-WEBB HOUSE, WEEDON HOUSE, WHYBURN HOUSE, WOODY HOUSE, YEN HOUSE
    Affected Utilities: Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW, Building Steam MTHW
    Reason: Annual Main Steam Plant Outage
  19. 6/26/2021 6:00:00 AM thru 6/26/2021 6:00:00 PM
    Affected Buildings: HEATING PLANT
    Affected Utilities: Electricity Normal Power,Emergency Power
    Reason: North Chiller Plant Switchgear Replacement - New switchgear is in place and will be tested on 6/26