Monday, October 26: The sidewalk entrance to the D3 parking lot near the JAG and Law Schools will be closed for concrete repairs to address potential trip hazards.
Saturday, October 31: The intersection on Massie Road near the Law School and JAG/D3 parking lot will undergo milling and paving. This work is scheduled to be completed in one day, with one lane remaining open to maintain vehicular access.
Monday, November 2: Thermoplastic crosswalk markings will be installed during overnight work, with crews beginning at 7:00 p.m.
Rooterman will be making the SIPP liner repair to the sanitary sewer forced main at Special Collections on Tuesday (10-20-2026) with the work anticipated to take up to 8hrs. Some stairs/sidewalks will be blocked, but appropriate signage for pedestrian access/direction will be provided.
Work blocks existing sidewalks and was reviewed with OUBO prior to blockage.
Pedestrians: Beginning on October 12 through November 9, a portion of the north promenade will be closed due to utility tie-ins.
Vehicles: Expect occasional delays entering and exiting the garage due to construction vehicles on Rothery Road as the primary project entrance and exit.
Beginning Monday August 24th, the parking lot in front of the Physical & Life Sciences Building and Chemistry Addition, between Chemistry Drive and Geldard Drive, will be closed for the duration of this project.
The lot will be reopened in August of 2027.
Sidewalks around the perimeter of the site will not be impacted.
Access to building entrances and exits will be maintained.
As part of the enabling work for the Fontaine Data Center, FM Energy & Utilities will continue installing underground utilities from the FCEP to the future data center site. Phase One has been under construction since May and the team will transition to Phase Two on July 13. This work is located east of 500 Ray C Hunt.
Phase Two will begin on July 13 and take four to five months to complete. Patient parking will be significantly impacted but mitigated with the following services:
Complementary Valet Service will be offered to patients at 500 RCH; Additional golf carts will be used to assist with patient transport. Concierge staff will be onsite to assist patients to parking.
Patient parking spaces will be available directly west of FCEP. Access to the Building 500 loading dock will be maintained.
Signage will be added to assist with vehicular and pedestrian signage.
All work is subject to weather conditions.
No impact to existing building exits and sidewalks.