Skip to main content

Construction alerts

  • July 22-26, 2024 — University Ave area affected
    University Ave Stone Wall Construction — alert 1
    • Contractor will be repairing the stone wall running parallel with University Ave. Repair work will begin on Monday, July 22 through Friday, July 26. University Ave. will periodically be reduced to one lane due to the repairs. Flaggers will be present to help control the flow of traffic during lane closures. No sidewalks will be impacted during this work.
  • July 1-December 1, 2024 — Fontaine Research Park area affected
    UVA Manning Institute of Biotechnology — alert 16
    • Scope of Work: 7/1/2024-12/1/2024
      • Fencing has been adjusted to open a new pedestrian path from Snyder to Aurbach.
      • Parking in front of Snyder has been restriped to allow for consolidation of the ADA parking for Snyder and Aurbach (8 spots total).
      • Excavation will continue until September, followed by concrete foundation work and steel erection.
    • Scope of Work: 7/15/2024-9/15/2024
      • Work will take place for a new sanitary sewer line from Snyder/Aurbach down to the existing RWSA line. This will temporarily close a section of the Rivanna Trail.
      • 7/26/2024 From 08:00a - 11:00a, there will be temporary crane loading/staging happening in front of Aurbach. There will be short, intermittent stoppages of pedestrian traffic on the path as material is craned into place over the path. The team will have personal onsite to manage the situation and stop foot traffic while loads are being flown.
      • 8/3/2024 (Saturday) - There will be an 8 hr outage (07:00a - 15:00p) for Domestic Water and Steam at Aurbach.
      • Pedestrian and delivery access to all buildings will be maintained throughout all phases of work.
      • Diagrams of impacts are included below for all phases of work.
  • June 28-August, 2024 — Key Alley area affected
    East Lawn Roof and Railing - Pavilion VI-VIII — alert 1
    • On June 28, 2024, scaffolding will be constructed in the stairwell heading to the Key Alley parking court between Pavilions VI and VIII. The scaffolding will leave appropriate means of access and will have a handrail installed. The scaffolding will remain in place for three weeks.
    • Work blocks existing sidewalks, and was reviewed with OUBO prior to blockage.
  • May 28-August 16, 2024 — Mechanical Engineering, Jesser Hall area affected
    Jesser Hall Capstone Replacement & Window Abatement/Replacement — alert 2
    • Parking Lot west of Mechanical Engineering: Beginning Tuesday May 28 the parking lot behind Mechanical Engineering will be closed off to provide a laydown area for the work at Jesser Hall. The parking lot will be closed off to vehicle access until August 16th.
    • Jesser Hall: Starting on Tuesday May 28, scaffolding will be erected around the entire perimeter of Jesser Hall. There will be overhead protection provided on all sidewalks. All entry and egress into the building will be maintained with covered walkways. The loading dock area will be blocked with scaffolding and a dumpster for the duration. All scaffolding, dumpsters, and construction materials are expected to be removed by August 16th.
    • No impact to existing building exits and sidewalks.
  • May 28-August, 2024 — High Energy Physics area affected
    Jesser Hall Capstone Replacement & Window Abatement/Replacement — alert 1
    • Parking Lot west of Mechanical Engineering: Beginning Tuesday May 28th the parking lot behind Mechanical Engineering will be closed off to provide a laydown area for the work at Jesser Hall. The parking lot will be closed off to vehicle access until the last week of July.
    • Jesser Hall: Starting on Tuesday May 28th, scaffolding will be erected around the entire perimeter of Jesser Hall. There will be overhead protection provided on all sidewalks. All entry and egress into the building will be maintained with covered walkways. The loading dock area will be blocked with scaffolding and a dumpster for the duration. All scaffolding, dumpsters, and construction materials are expected to be removed by the 2nd week of August.
  • May 20-Fall 2024 — Whispering Wall Plaza area affected
    Central Grounds Accessible Path, Phase 1 (Newcomb South) — alert 2
    • Pedestrians: A small portion of the Whispering Wall Plaza behind Monroe Hall will be coned off the week of May 20th for construction equipment. See map.
    • Pedestrians: Fencing will be installed around the project area starting on Monday, May 20th and will remain until Fall 2024. The pedestrian path between the construction area and Newcomb Hall will remain open throughout the duration of this project.
  • May 20-August 16, 2024 — Physics Building area affected
    Physics Building Renovation — alert 12
    • Jamerson-Lewis Construction will be installing gates and existing bollards for construction and emergency vehicle access only to the rear R-2 parking lot behind Physics. The parking lot will be closed to pedestrians starting Monday, May 20 and return to service on Friday, August 16. This closure is to complete utility work, hard scape, curb/sidewalk and paving scope for Phase 3.
  • May 22-August 1, 2024 — East Range Dorm, Hotel D areas affected
    Hotel B Low Temperature Hot Water Repair — alert 1
    • SL. Williamson Inc. will be installing a temporary roadway in front of the East Range Dorm and Hotel D for visitors as well as all emergency response vehicles beginning on (5/22/2024-5/29/2024) that will connect Rotunda Alley to Green Alley.
    • Utility Distribution teams will mobilize on Tuesday (6/11/2024) and close Rotunda Alley between Hotel B/East Range Dorm and establish site fencing in the area with appropriate signage. Vehicular traffic will begin using the temporary roadway at that point.
    • Utility Distribution teams will make the necessary repairs and anticipate the construction phase to be completed between (6/11/2024-8/1/2024) at which point Rotunda Alley will be reopened upon completion.
  • May 20-August, 2024 — Runk Patio, residence halls area affected
    Hereford College 4 Pipe Utility Extension — alert 1
    • Phase 1A directional drill pipe installation at Runk Patio starting 20 May 2024.
    • Phase 1A sidewalk closure at Breezeway between Norris, Malone and Johnson Residence Halls starting 27 May through early August.
    • Phase 1B sidewalk impact at the rear of Weedon and Whyburn Residence Halls starting early July-September
    • Phase 2 to impact Hereford Lawn area starting late September-December.
    • Phase 3 to impact Johnson Residence Hall November 2024-January 2025.
    • Schedule to coincide with various ongoing projects within the vicinity and are subject to change with alerts to accommodate.
    • Utility outages to be scheduled and coordinated with HRL for service tie-ins.
  • May 20-August 15, 2024 — Alderman Rd., O-Hill area affected
    Low Temperature Hot Water (LTHW) Phase 3A
    • The project team will be mobilizing construction areas west of Alderman Road the morning of Monday 5/20.
    • All parking in front of O-Hill Dining will be closed and fencing will be installed around the perimeter of the parking spaces. Parking will re-open no later than August 15.
    • The area in front of Watson-Webb dorm that was recently demobilized will be fenced off once again.
    • A small section of construction fencing will be installed in the sidewalk between Lile-Maupin, Tuttle Dunnington and O-Hill Dining.
    • See attached alert for map of affected area.
  • March 25, 2024-Fall, 2025 — Fontaine Research Park Parking Garage area affected
    Fontaine Research Park Parking Garage Project — alert 2
    • In support of the Fontaine Research Park Parking Garage Project, a site enabling project is required to provide a new pedestrian sidewalk for building egress and to relocate ADA parking associated with the 400 Ray C Hunt Drive building.
    • Starting on Monday, March 25, 2024, the contractor will mobilize on site to start the installation of the new pedestrian sidewalk. The contractor will install perimeter construction safety fence to encompass the landscaped area at the Southwest corner of the 400 Ray C Hunt Drive building. See Exhibit 1 on page 2 of this construction alert.
    • After the new pedestrian sidewalk has been installed, the contractor will start the installation of the new ADA parking associated with the 400 Ray C Hunt Drive building. The contractor will install perimeter construction safety fence to encompass the roundabout area at the Southwest corner of the 400 Ray C Hunt Drive building. See Exhibit 2 on page 3 of this construction alert.
    • There will be typical construction equipment noise associated with this work.
    • All building means of egress will be maintained during construction.
  • January-July 30, 2024 — Alderman Rd., Scott Stadium area affected
    Scott Stadium Video Board Upgrade — alert 1
    • Future intermediate road closures likely and will be communicated with future alerts.
    • Alderman Road east drive lane and east sidewalk temporary intermediate closures
    • Fenced no parking area through 07.30.2024
  • January 15-December, 2024 — Crispell Dr. area affected
    UH Guided Ultrasound & MRI Relocation — alert 1
    • Starting Monday, 1/15/24, a contractor will begin assembling fencing and scaffolding in the emergency vehicle parking spaces along Crispell Dr.
    • Crispell Dr will remain open in both directions, there will be temporary lane closures with flaggers to direct traffic to allow safe fabrication of construction fencing.
    • Crispell Dr sidewalk will always remain open. Spotters will be onsite to ensure pedestrian safety during fencing and scaffolding assembly.
    • Fencing and scaffolding will be in place from 1/15/24 through December 2024
  • October 16, 2023-Summer, 2024 — Thornton Hall, Stadium Rd. area affected
    Low Temperature Hot Water (LTHW) Phase 3B
    • The parking lot on the northeastern side of Thornton known as East J will be closed and construction fence will be put up Monday, October 16.
    • Egress from all exits from the building and pathways for pedestrian travel through the lot will be maintained. However, the lot will be closed to all non-construction related vehicles.
    • The sidewalk between Thornton and Stadium Road will be closed, and an alternate pedestrian route will be provided.
    • This phase of the project is scheduled to be completed in the summer of 2024.

Interactive construction map

Click on each project to view more details.

This interactive construction map is in development, for questions or feedback about the map please contact Molly Shifflett, project associate with Capital Construction & Renovations.