Numerous tunnel access points from Garrett Hall to Davis Wing will be used for asbestos insulation removal and reinsulating of existing piping was asbestos removal is complete. All access points will not be open simultaneously.
A portion of the accessible sidewalk between Newcomb Road and Peters House will be
closed on Wednesday March 18, 9:30 a.m.-5:30 p.m. to perform (additional) Utility
Test Pits Survey Work for the future project. The sidewalk area where a Vacuum Truck
will be located will be partially open and accessible, with cones and signage directing
pedestrian traffic around the area of the parked truck.
Grinding a small section of concrete near the entrance of the building to repair a trip
hazard. Crews will be working on a 2ft section at a time to allow full access to the
entrance and sidewalk. Crews will begin work on Wednesday, March 11.
Starting Monday March 16th through April 2nd we will be replacing three existing cooling towers that serve the Chemistry Chiller Plant. Geldard Dr will be limited to one lane during loading of the old towers and unloading the new towers during this project. Access to AFC loading dock will be open for AFC deliveries only and will be closed the remaining time. The sidewalk closest to the AFC will be closed during the duration of the project.
Work blocks existing sidewalks.
January-April, 2026 — Jefferson Park Avenue and Stadium Road areas affected Verve — alert 7
Between January 2026 and April 2026, there will be four scheduled road closures/modifications along Jefferson Park Avenue (northbound and southbound) and Stadium Road (northbound and southbound). During each closure/modification, detour signage and flaggers will be in place to maintain safe and efficient traffic flow. The attached map shows the impact.
Pedestrians: The current pathways on Stadium Rd., Emmet St., and JPA will remain in place until Q3 2027.