Phase 1. Emmet St. between Stadium Road and the JPA intersection will be
CLOSED from November 16th through November 30th but open November 25-27. Football home games - all roads will be open.
Phase 2. JPA southbound (along the building property line) will be closed from November 30th through December 18th.
December 9, 2026 - January 20, 2027: A portion of Copeley Road will be closed to both vehicular and pedestrian traffic to accommodate a sidewalk expansion and waterline replacement project.
No impact to existing building exits and sidewalks.
Wednesday, November 11: The intersection on Massie Road near the Law School and JAG/D3 parking lot will undergo milling and paving. This work is scheduled to be completed in one day, with one lane remaining open to maintain vehicular access. Work is scheduled to be completed by 8am
Thursday, November 12: Thermoplastic crosswalk markings will be installed during overnight work, with crews beginning at 7:00 p.m.
Beginning Thursday, November 5 through Friday, November 13, a portion of McCormick Road and the south sidewalk will experience temporary modifications due to storm water inlet installation work (McCormick Rd.) and concrete pours (sidewalk).
McCormick Road will remain open throughout the work. Flaggers will be on site to assist
with traffic, but motorists should expect minor delays.
Work blocks existing sidewalks.
No impact to existing building exits and sidewalks.
November 16 - The MIoB project team will adjust the site fencing to capture the line of parking in front of the Snyder research facility. The ADA parking in this area will be relocated into two new locations.
As part of the MIoB project, the team will be milling the existing asphalt parking and replacing the waterproofing on the roof of the LiSA facility. This will require the use of hot rubber membranes.
The removal of asphalt and concrete will produce noise, vibrations and dust. The application of hot rubber waterproofing will produce odors that may be perceived outside the project site.
November 30 - The MIoB project team will begin cutting through the exterior concrete wall of the Life Science Annex (LiSA Facility) in Fontaine Research Park. This demolition will be followed by additional construction activities for installation of new doors and finishes for the connecting tunnel between LiSA and the MIoB project.
This work will entail cutting and chipping of concrete, and though the dust and debris will be contained, there will be loud noise and vibrations during the initial part of this work. We anticipate the major noise/vibration to last 1-2 weeks.
There will be enabling work preceding the start of cutting. This includes installation of a temporary wall barrier on the LiSA side to contain dust and debris. This enabling work will start the week of November 9, 2026.
No impact to existing building exits and sidewalks.
Monday November 2, 2026 will begin demolition of landscaping, trees, and walking paths for the renewal of Thaler Garden; located adjacent to the West Complex Loading Dock and highlighted in yellow on the attached map.
Foot traffic into the garden, including the building stairwell exit, will be closed off and restricted to construction personnel.
Please be aware of increased vehicle and foot traffic in the West Complex loading dock area, highlighted in red on the attached map.
Thaler Garden is expected to reopen Friday January 29, 2027.
Beginning Monday August 24th, the parking lot in front of the Physical & Life Sciences Building and Chemistry Addition, between Chemistry Drive and Geldard Drive, will be closed for the duration of this project.
The lot will be reopened in August of 2027.
Sidewalks around the perimeter of the site will not be impacted.
Access to building entrances and exits will be maintained.
As part of the enabling work for the Fontaine Data Center, FM Energy & Utilities will continue installing underground utilities from the FCEP to the future data center site. Phase One has been under construction since May and the team will transition to Phase Two on July 13. This work is located east of 500 Ray C Hunt.
Phase Two will begin on July 13 and take four to five months to complete. Patient parking will be significantly impacted but mitigated with the following services:
Complementary Valet Service will be offered to patients at 500 RCH; Additional golf carts will be used to assist with patient transport. Concierge staff will be onsite to assist patients to parking.
Patient parking spaces will be available directly west of FCEP. Access to the Building 500 loading dock will be maintained.
Signage will be added to assist with vehicular and pedestrian signage.
All work is subject to weather conditions.
No impact to existing building exits and sidewalks.