Construction alerts

  • November 7-9, 2018 – Massie Road, The Park affected
    Track & Field Membrane Structure Project – alert 1
    Wednesday November 7th through Friday November 9th tie-in to the existing waterline in Massie Road will be ongoing. Domestic water to The Park will be shut down on Wednesday, November 7th from 7am-5pm. Southbound lane exiting The Park will be closed each day from the 7th through the 9th from 7am-5pm. There will be flagmen posted to direct traffic during those hours. The southbound lane will be plated and open each evening after 5pm.
  • November, 2018 - April, 2019 – East Lawn, East Range affected
    East Range Stormwater Management – alert 11
    Continuing unforeseen utility conflicts in Lile Alley have further impacted the phasing plan and overall project schedule. Lile Alley paving is currently scheduled for November 1-2, weather dependent.
  • September 19 - October, 2018 – South Lawn Access Drive affected
    Brandon Avenue Green Street & Utilities – alert 16
    Utility installations in the South Lawn Access Drive will be starting on Wednesday, 9/19/18. The contractor is planning on performing this work at night, and will plate the excavation during the day to allow vehicles to pass through the area. This work is expected to last approximately 2 weeks.
  • September 10 - October 19, 2018 – Patterson Alley and Colonnade Alley affected
    Lawn Accessibility Project – alert 9
    Masons will begin installing brick walls at the ramp adjacent to Pavilion V. Upon completion of the walls, a second crew will begin installing brick pavers at the Pavilion V ramp while the wall crew moves to the ramp adjacent to Pavilion IX. The ground crew will follow upon completion.
  • September 11 - October, 2018 – Pavilions V - III affected
    West Lawn Roof & Railing Replacement Project - alert 4
    Expect temporary closures to the colonnade sidewalk and access to Poe Alley from the Lawn. The ceiling of the colonnade in between Pavilions V – III will receive a traditional 3-coat plaster system. Schedule: Plastering work will begin on Tuesday, September 11th. Workdays are typically 8:00am – 3:30pm.
    The installation of this plaster ceiling will require several days of activity for each coat of plastering. In between the installation of each coat will be a period of inactivity while each coat cures before the next coat can be installed. The curing period is highly dependent on weather and humidity conditions. The overall process is expected to take about a month.
  • December 10, 2018 - September, 2019 – Brooks Hall area affected – Memorial to Enslaved Laborers
    Memorial to Enslaved Laborers - alert 2
    On December 10, Team Henry Enterprises will mobilize to install fencing and a temporary construction access road within the Triangle of Grass to facilitate construction of the Memorial to Enslaved Laborers. Construction will consist of significant site work, including re-grading, utilities, concrete foundation work, stormwater and sidewalk improvements, and installation of large-scale stone blocks. Pedestrian routes within the site will be blocked. As fencing is installed and sidewalks become blocked, way-finding signage will be installed to indicate new routes for pedestrians.
  • October 1, 2018 - January, 2020 – Massie Road area affected – Softball Stadium & Player Development Center
    Softball Stadium construction - alert 2
    Sidewalk closure along the south side of Massie Road. Sidewalk will be close from Thursday October 18, 2018 until January 2020. Signage will be provided at both ends of the sidewalk to acknowledge the closure and give direction to pedestrians for an alternate route.
  • April 30, 2018 - Summer, 2023 – U-Hall cage lot affected
    Cage lot map
    To support a significant construction project in U-Hall, the Cage lot will be closed beginning Monday, April 30th through the Summer of 2023. As a result, the University Transit Service (UTS) bus stops near the Cage lot and in the West University Hall lot will be closed for the duration of this project. The UTS Bus stops on Massie Road at University Hall and the East Lot will remain open.

Major construction projects map

UVA Parking & Transportation detours and lot closures