As part of the Fontaine Research Park Sitewide Stormwater Improvements project, the contractor must install new stormwater utility infrastructure and make the tie-in for what was installed as part of the Roadway Infrastructure project at the intersection of Spine Road and Ray C Hunt Drive.
On Monday, May 18, the contractor will mobilize to start this work. This work will require the intersection of Spine Road and Ray C Hunt Drive to be closed to thru traffic. The working hours will be 8:00PM - 5:00AM to avoid any disruptions during normal hours at Fontaine and will have a duration of three (3) weeks. See Exhibit 1 on page 3, area of work is shown in red. The pedestrian pathway is shown in yellow.
During this work, Fontaine Research Park shuttle on demand after-hours users who normally use the pickup location at 480 Ray C Hunt Drive will need to use the pickup locations at either 415 or 500 Ray C Hunt Drive. Signage will be posted.
Parking will be prohibited in the lower southern parking spaces of Spine Road, five (5) on each side.
There will be typical construction equipment noise associated with this work.
All buildings will maintain their means of egress.
This work is subject to change due to weather conditions. A revised construction alert will be sent accordingly.
As part of the enabling work for the Fontaine Research Data Center, FM Energy & Utilities will begin installing underground utilities from the FCEP to the future data center site on May 4, 2026. This work is located to the east of 500 Ray C Hunt.
Phase One will begin May 4 and should be completed around July 4, 2026. Fourteen total parking spaces will be impacted during this phase.
Additional golf carts will be used to assist with patient transport. Patient parking spaces will be available directly west of FCEP. Access to the Building 500 loading dock will be maintained.
As part of the Fontaine Research Park Parking Garage Project, rework is required in connection with the vehicular bollards at the southeast concrete pedestrian crossing. This work will be phased to maintain pedestrian accessibility.
Phase 1 is scheduled to start Monday, April 27. See Exhibit 1 on page 2, area of work is shown in red. The pedestrian pathway is shown in yellow. This work will be completed by Friday, May 1.
Phase 2 is scheduled to start Monday, May 4. See Exhibit 2 on page 2, area of work is shown in red. The pedestrian pathway is shown in yellow. This work will be completed by Friday, May 8.
There will be typical construction equipment noise associated with this work.
All buildings will maintain their means of egress.
This work is subject to change due to weather conditions. A revised construction alert will be sent accordingly.
Southbound lane of Copeley Rd. will be closed from Peyton Ct. to Massie Rd. between April and mid-May. The northbound lane of Copeley Rd. will remain open.
Pedestrian traffic will be allowed along Copeley Rd. between Peyton Ct. and Massie Rd.
During this time, daytime work will also occur at the northwest corner of Copeley Rd. and Massie Rd. Traffic signal adjustments and flaggers will be present from approximately 8:00 am to 3:00 pm. daily, Monday to Friday.
Short term adjustments will be made to accommodate events at the JPJ Arena.
Flaggers, signage and cones will be established to direct traffic and pedestrians around the closures.
Numerous tunnel access points from Garrett Hall to Davis Wing will be used for asbestos insulation removal and reinsulating of existing piping was asbestos removal is complete. All access points will not be open simultaneously.