There will be a full electrical shutdown of FM Shops #2, FM Shops #3, FM Shops #4, and the FM Truck Washout Building from 8:30am Wednesday 17-Dec until work is completed at the end of the day Saturday 20-Dec. Approx 4pm.
Please plan to vacate the buildings by 8:30am Wednesday morning. They will remain unlocked and have minimal egress lighting supplied in the main corridors. Temporary heat will also be supplied.
There will be a full electrical shutdown of FM Shops #1on Wednesday 17-Dec from 8:30am until 11:30am. There will be no temp lighting supplied during this time. Some emergency lighting will be functional.
There will be an additional full electrical shutdown of FM Shops #1 on Saturday 20-Dec all day from 6am until 4pm or when the work is completed.
Please also avoid the area near the FM Truck Washout Building during this time as there will be a lot of activity by Power & Light and C&RS Electricians.
No impact to existing building exits and sidewalks.
The east bound lane of Massie Rd in between JPJ Arena and Olympic Sports Complex(OSC) will be shifted over to accommodate a crane for delivery of items to the OSC Roof.
During this time, Massie Rd will be down to one lane in each direction from approximately 7:00 am to 2:00 pm.
Flaggers, signage and cones will be established to direct traffic and pedestrians around the closures.
Work blocks existing building exits.
Work blocks existing sidewalks.
December 2025-March 2026 — Jefferson Park Avenue area affected Verve — alert 4
Between December 2025 and March 2026, there will be four scheduled road closures/modifications along Jefferson Park Avenue (northbound and southbound) and Stadium Road (northbound and southbound). During each closure/modification, detour signage and flaggers will be in place to maintain safe and efficient traffic flow. The attached map shows the initial impact. The additional impact dates are also included, and maps will be sent separately closer to the construction start dates.
Pedestrians: The current pathways on Stadium Rd., Emmet St., and JPA will remain in place until Q3 2027.
The roof will be replaced in 2 phases. The building highlighted below in orange will be
phase 1. There is already scaffolding built around this building. It will remain until it is
moved to phase 2 building in December. A 2nd alert for phase 2 will be sent out in November.
During phase 1 the receiving warehouse will be condensed only to operate in only the blue
building below. Anyone besides the warehouse crew will not have access to the phase 1
building for the next 4 weeks while overhead welding and spray foam is completed. This
impacts all the material storage in the phase 1 building.