Utility outages

In order to perform necessary maintenance, inspection or equipment modifications, interruptions in building services or systems will take place. In all cases, every attempt will be made to keep the inconvenience to a minimum. If you have any questions, please contact one of Facilities Management’s service desks:

Academic division
(434) 924-1777

Health system division
(434) 924-2267

Outage Subscription Manager

Planned & Emergency Utility Outages


  1. 2/6/2026 2:00:00 PM thru 3/16/2026 10:30:00 AM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: Chilled Water
    Reason: MRI #3 - Replacement - Project
  2. 2/6/2026 2:30:00 PM thru 3/16/2026 2:30:00 PM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: Electricity
    Reason: MRI #3 - Replacement - Project
  3. 2/28/2026 5:00:00 AM thru 2/28/2026 3:00:00 PM
    Affected Buildings:
    Affected Utilities: Domestic Water
    Reason: Maintenance
  4. 2/28/2026 6:00:00 AM thru 2/28/2026 10:00:00 AM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: HVAC
    Reason: Shell Space Room 1038 - Project
  5. 2/28/2026 6:00:00 AM thru 2/28/2026 10:00:00 AM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: Electricity
    Reason: UH Guided Ultrasound & MRI Expansion - FACP22 042 - Project
  6. 2/28/2026 7:00:00 AM thru 3/1/2026 4:00:00 PM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: Fire Alarm System
    Reason: UH Fire Alarm Annunciation Replacement Phase 2 FACP22 003 - Project
  7. 2/28/2026 7:00:00 AM thru 3/6/2026 7:00:00 AM
    Affected Buildings: BAYLY BUILDING, CAMPBELL HALL, CARR'S HILL / PRESIDENT'S HOUSE
    Affected Utilities: Chilled Water, Chilled Water, Chilled Water
    Reason: Campbell Hall Electrical Service Replacement - Campbell Hall Switch gear and emergency back up install
  8. 2/28/2026 7:00:00 AM thru 3/6/2026 4:00:00 PM
    Affected Buildings: CAMPBELL HALL, CARR'S HILL FIELD SUPPORT FACILITY, CHW DISTRIBUTION SYSTEM @ CARR'S HILL, DRAMA EDUCATION BUILDING
    Affected Utilities: Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power)
    Reason: CS: Campbell Hall Electrical Service Replacement - Switch gear replacement.
  9. 3/2/2026 6:00:00 AM thru 3/3/2026 6:00:00 PM
    Affected Buildings: CHEMISTRY BUILDING, CHW GENERATING EQUIPMENT @ CHEMISTRY BLDG
    Affected Utilities: Chilled Water, Chilled Water, Chilled Water
    Reason: Replace leaking flange and associated pipe within the basement level of Chemistry Addition.
    • Contact:     
  10. 3/3/2026 7:00:00 AM thru 3/3/2026 9:00:00 AM
    Affected Buildings: MOLLY AND ROBERT HARDIE FOOTBALL OPERATIONS CENTER
    Affected Utilities: Fire System Fire System Panel
    Reason: Football Operations Center - Fire Alarm and AV interface testing in S&C.
  11. 3/4/2026 7:00:00 AM thru 3/4/2026 8:00:00 AM
    Affected Buildings: MECHANICAL ENGINEERING
    Affected Utilities: Electricity Normal Power
    Reason: To install a new breaker and connection to the circuit for the exhaust fan in room 109.
  12. 3/6/2026 10:00:00 AM thru 3/6/2026 12:30:00 PM
    Affected Buildings: PHYSICS/JESSE BEAMS LABORATORY
    Affected Utilities: Electricity Normal Power
    Reason: Physics Building Renovation - Cx Facilities Dynamics will perform a blackout test for Final Commissioning.