In order to perform necessary maintenance, inspection or equipment modifications, interruptions in building services or systems will take place. In all cases, every attempt will be made to keep the inconvenience to a minimum. If you have any questions, please contact one of Facilities Management’s service desks:

Academic division
(434) 924-1777

Health system division
(434) 924-2267

Outage Subscription Manager

Planned & Emergency Utility Outages


  1. 5/26/2020 7:00:00 AM thru 6/5/2020 5:00:00 PM
    Affected Buildings: LAMBETH FIELD #50, LAMBETH FIELD #51, LAMBETH FIELD #52, LAMBETH FIELD #53, LAMBETH FIELD #54, LAMBETH FIELD #55, LAMBETH FIELD #56, LAMBETH FIELD #57, LAMBETH FIELD #58, LAMBETH FIELD #59, LAMBETH FIELD #60, LAMBETH FIELD #61, LAMBETH FIELD #62, LAMBETH FIELD #63, LAMBETH FIELD #65, LAMBETH FIELD #66, LAMBETH FIELD #67, LAMBETH FIELD #68, LAMBETH FIELD #69, LAMBETH FIELD #70, LAMBETH FIELD #71, LAMBETH FIELD #72, LAMBETH FIELD #73, LAMBETH FIELD #74, LAMBETH FIELD #75, LAMBETH FIELD COMMONS
    Affected Utilities: Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power)
    Reason: Lambeth Apartment HVAC Upgrade - Lambeth Field #50,Lambeth Field #51,Lambeth Field #52,Lambeth Field #53,Lambeth Field #54,Lambeth Field #55,Lambeth Field #56,Lambeth Field #57,Lambeth Field #58,Lambeth Field #59,Lambeth Field #60,Lambeth Field #61,Lambeth Field #62,Lambeth Field #63,Lambeth Field Commons,Lambeth Field #65,Lambeth Field #66,Lambeth Field #67,Lambeth Field #68,Lambeth Field #69,Lambeth Field #70,Lambeth Field #71,Lambeth Field #72,Lambeth Field #73,Lambeth Field #74,Lambeth Field #75
    • Contact:     
  2. 5/26/2020 7:00:00 AM thru 6/20/2020 4:00:00 PM
    Affected Buildings: AQUATIC & FITNESS CENTER
    Affected Utilities: HVAC
    Reason: LTHW Phase 1A - Conversion to LTHW.
  3. 5/27/2020 7:00:00 AM thru 6/18/2020 5:00:00 PM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: Elevator
    Reason: ED Operating Rooms & Bed Tower Addition - Project
  4. 6/1/2020 7:00:00 AM thru 6/3/2020 3:30:00 PM
    Affected Buildings: CAMPBELL HALL
    Affected Utilities: Fire System - Sprinkler System
    Reason: Campbell Hall 1st Floor - We will be installing sprinkler heads on Campbell 1st Floor
  5. 6/1/2020 7:00:00 AM thru 6/4/2020 5:00:00 PM
    Affected Buildings: UNIVERSITY HOSPITAL
    Affected Utilities: Elevator
    Reason: ED Operating Rooms & Bed Tower Addition - Project
  6. 6/2/2020 7:00:00 AM thru 6/4/2020 6:00:00 PM
    Affected Buildings: 2400 OLD IVY ROAD
    Affected Utilities: HVAC
    Reason: 2400 Old Ivy Road Low-Slope Roof Replacement and EIFS Repair - As part of roof replacement, abandoned rooftop equipment needs to be removed, and remaining equipment needs to be raised to accommodate additional insulation and roof slope.
  7. 6/2/2020 7:00:00 AM thru 6/5/2020 3:30:00 PM
    Affected Buildings: GILMER HALL
    Affected Utilities: Fire System - Sprinkler System
    Reason: Gilmer Chemistry Renovation - Gilmer Outage - Gilmer Rolling Outage - This outage is being done to allow VSC to turn up heads on Gilmer Level 1 ( New Level 3) in preparation of construction activities.
  8. 6/2/2020 7:00:00 AM thru 6/9/2020 4:00:00 PM
    Affected Buildings: DARDEN CLASSROOM
    Affected Utilities: HVAC
    Reason: Darden iLab - We will be sawcutting the tiered concrete flooring system in Darden Classrooms 180 and 190.
  9. 6/2/2020 8:00:00 AM thru 6/5/2020 5:00:00 PM
    Affected Buildings: PINN HALL
    Affected Utilities: HVAC
    Reason: Pinn Hall Lab Renovation – Phase 1 - Project
  10. 6/3/2020 7:00:00 AM thru 6/4/2020 3:30:00 PM
    Affected Buildings: CHEMISTRY BUILDING
    Affected Utilities: Fire System - Sprinkler System
    Reason: Gilmer Chemistry Renovation - Chemistry Outage - Old Chemistry - This outage is being done to allow ACI to tie-in sprinkler piping at the SW Shaft and to relocate sprinkler piping in the Penthouse bathroom.
  11. 6/3/2020 7:00:00 AM thru 6/5/2020 3:30:00 PM
    Affected Buildings: GEORGE WELSH INDOOR PRACTICE FACILITY
    Affected Utilities: Fire System - Fire Suppression
    Reason: Athletics Complex Phase I - To allow new fire line service piping to be installed in IPF.
  12. 6/3/2020 8:00:00 AM thru 6/3/2020 2:00:00 PM
    Affected Buildings: PINN HALL
    Affected Utilities: Fire Alarm System
    Reason: Pinn Hall Lab Renovation – Phase 1 - Project
  13. 6/3/2020 8:00:00 AM thru 6/3/2020 2:00:00 PM
    Affected Buildings: PINN HALL
    Affected Utilities: Fire Alarm System
    Reason: Pinn Hall Lab Renovation – Phase 1 - Project
  14. 6/3/2020 9:00:00 AM thru 6/3/2020 12:00:00 PM
    Affected Buildings: CHEMISTRY BUILDING
    Affected Utilities: Electricity - Emergency Power
    Reason: Gilmer Chemistry Renovation - Chemistry Outage - Old Chemistry - This outage is being done to allow Design Electric to install the remaining CTs in Distribution Panel MLB. This affects emergency power for multiple subpanels.
  15. 6/4/2020 7:00:00 AM thru 6/4/2020 3:00:00 PM
    Affected Buildings: GILMER HALL
    Affected Utilities: Building Steam -
    Reason: Gilmer Chemistry Renovation - Gilmer Outage - Gilmer - This outage is being done to allow Riddleberger to cut/cap the steam and condensate piping at the heat exchangers in the Gilmer West Basement Mechanical Room.
  16. 6/4/2020 7:00:00 AM thru 6/5/2020 4:00:00 PM
    Affected Buildings: WEST RANGE DORMS
    Affected Utilities: Fire System - Sprinkler System
    Reason: Hotel C Drainage and Addstone Project - In order to install site drainage pipe and structures thrust block that supports 6" sprinkler feed below Hotel C will need to be drained and taken out of commission for 2 day. Drained on Thursday May 4th 7am and brought back online Friday May 5th at 4pm.
  17. 6/4/2020 8:00:00 AM thru 6/4/2020 5:00:00 PM
    Affected Buildings: PINN HALL
    Affected Utilities: HVAC
    Reason: Pinn Hall Lab Renovation – Phase 1 - Project
  18. 6/5/2020 7:00:00 AM thru 6/5/2020 4:00:00 PM
    Affected Buildings: BOND HOUSE
    Affected Utilities: Fire System - Smoke Detection
    Reason: Install Plexiglas walls in north and south stairs. - Will be welding in the north and south stairs on level 1.
  19. 6/8/2020 7:00:00 AM thru 6/26/2020 6:00:00 PM
    Affected Buildings: BONNYCASTLE HOUSE, DABNEY HOUSE, KENT HOUSE
    Affected Utilities: Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power), Electricity (Normal and Emergency Power)
    Reason: McCormick Road Houses Renovation - Sever electrical connections in order to reconnect to new project transformer.
  20. 6/23/2020 7:30:00 AM thru 6/23/2020 2:30:00 PM
    Affected Buildings: FONTAINE MEDICAL OFFICE BUILDING 1
    Affected Utilities: Fire Alarm System
    Reason: MRI Replacement 415 Fontaine - Project

Major construction traffic map »