To provide support for the building during construction, shoring will be reconfigured December 1-December 5.
Remaining construction activities will begin the following week, including closing of the eastern half of the stage.
Construction should be completed in March of 2026.
No impact to existing building exits and sidewalks.
December 2025-March 2026 — Jefferson Park Avenue area affected Verve — alert 4
Between December 2025 and March 2026, there will be four scheduled road closures/modifications along Jefferson Park Avenue (northbound and southbound) and Stadium Road (northbound and southbound). During each closure/modification, detour signage and flaggers will be in place to maintain safe and efficient traffic flow. The attached map shows the initial impact. The additional impact dates are also included, and maps will be sent separately closer to the construction start dates.
Pedestrians: The current pathways on Stadium Rd., Emmet St., and JPA will remain in place until Q3 2027.
The receiving warehouse roof is being replaced in 2 phases. The building highlighted below in orange is phase 1 and the blue highlight is phase 2. NOVEMBER 19-24, Wednesday through Monday, the scaffolding will be dismantled from phase 1 and rebuilt around phase 2. There will be major disruptions to the warehouse receiving and parking areas during those days.
During phase 2, the receiving warehouse will be condensed only to operate in only the orange building below. Anyone besides the warehouse crew will not have access to the blue building for the next 4-6 weeks while overhead welding and spray foam is completed. This impacts the uniform, clothing, & jackets area where the wonderful Mrs. Francine Chambers sits. She will reside in the orange highlighted building until Christmas break.
No impact to existing building exits and sidewalks.
The roof will be replaced in 2 phases. The building highlighted below in orange will be
phase 1. There is already scaffolding built around this building. It will remain until it is
moved to phase 2 building in December. A 2nd alert for phase 2 will be sent out in November.
During phase 1 the receiving warehouse will be condensed only to operate in only the blue
building below. Anyone besides the warehouse crew will not have access to the phase 1
building for the next 4 weeks while overhead welding and spray foam is completed. This
impacts all the material storage in the phase 1 building.
No impact to existing building exits.
August 13-Fall, 2025 — Jefferson Park Ave., Emmet St. area
affected The Verve — alert
2
Vehicles: Beginning Wednesday, August 13th, the intersection of
Jefferson Park Ave (JPA) and Emmet St., continuing to Stadium Rd., will be open to all vehicular traffic.
Pedestrians: The current pathways on Stadium Rd., Emmet St. and
JPA will remain in place until Q3 2027.
Upcoming Vehicular Impacts: In the upcoming weeks and months,
southbound JPA will be modified or fully closed (24/7) to allow continued storm and sewer
utility work. The specific duration and work hours are still being finalized. Once
confirmed, details will be shared through construction alerts.
Interactive construction map
Click on each project to view more details.
This interactive construction map is in development, for questions or
feedback about the map please contact Molly
Shifflett, project associate with Capital Construction & Renovations.