RECORD DOCUMENT SUBMISSION REQUIREMENTS
Updated:
Friday, October 02, 2009 02:12 PM
UVA RESOURCE CENTER REQUIREMENTS
Project Managers please review and send on to your A/E's.
These guidelines are informed by this
Supporting Documentation
At the end of each project, the Resource Center should receive:
-
A full set of printed Record Drawings produced by the A/E which incorporates
as-built markup from construction contractor. Record revisions should be indicated with
delta reference marks (not clouds), and the drawings should be properly annotated as
Record Drawings in the revision block of each sheet.
-
In lieu of a printed set, electronic submission of Record Drawings may be
permitted at the discretion of the FP&C Project Manager, and then only if they are submitted
according to the "Electronic Submission Guidelines" below.
-
A full set of CAD files for the drawings, each corresponding to a single drawing
sheet and having all of the x-refs bound to the file. If CAD fonts are utilized that are not
in the standard AutoCAD group, they should be embedded into the DWG. The CAD file name should
be the same as the sheet name. If you are working in a different CAD software package
(e.g. Microstation), please save all files as DWG format. Submission of PDF files is
appreciated and increasingly common, but not yet required.
-
One copy of the Record Project Manual, printed and bound, with electronic files
in Word or PDF format. Project Manual Record revision issue date should be marked on cover, and
specifications altered by addenda should be included in final (not marked-up) format.
Project Managers should be aware that:
-
Shop Drawings for life-safety topics and building automation should be forwarded to the
Resource Center where they will be archived, scanned, and kept in the collection.
-
Submittals for ALL DISCIPLINES including paint, ceiling
tiles, HVAC equipment, etc, should be sent to the Resource Center to be scanned and saved
instead of being sent to Fontana for long-term storage.
-
O&M Manuals for all equipment should be sent to the Resource Center to be
archived, scanned, and given to Facilities Operations or Health System Physical Plant to pass
on to the appropriate individuals.
ELECTRONIC SUBMISSION GUIDELINES
Preparation of Electronic Files for Printing
UVA CAD Layering Standards
UVA FM Civil CAD Standards 2008
UVA CAD Layers
United
States National CAD Standard
Please direct questions to:
Facilities Management Resource Center
Send us an email
or call (434) 982-5884
|